Time For A Reality Check:
 More Delays Are Coming
 For Georgia Power’s
 New Vogtle Reactors

Georgia Power executives certainly won’t say it and Georgia’s utility regulators certainly won’t acknowledge it, but the reality is there are going to be additional delays at Vogtle 3&4—the already delayed and over budget new nuclear project being built by Westinghouse for the Southern Company subsidiary and a consortium of Georgia municipal utilities south of Augusta.

In a process that resembles a Kabuki dance, every six months Georgia Power is required to file a construction monitoring report with the Georgia Public Service Commission detailing its progress and justifying its expenditures in the last reporting period. (Georgia Power filed its 14th such report, covering the six months from June-December of 2015, in February 2016; it is now pending before the PSC.) Intervenors get to comment during this process, but once that is done, like clockwork, the commission signs off on the report, the utility gets to charge ratepayers for the approved expenses and the whole process starts anew. However, when you look closely it is clear that all is not well with the long-running Vogtle production.

In particular, it is worth taking a long look at the testimony presented by Dr. William Jacobs and Steven Roetger, who represent the Georgia PSC’s public interest advocacy staff in overseeing construction activities at Vogtle. Jacobs is the project’s independent construction monitor and has raised questions about the plant’s construction schedule virtually since the first dirt was turned (see this story). Roetger is the leader of the staff’s oversight team and has been involved with the project since the beginning. We will get into the details of their testimony below, but their conclusion is striking:

“We conclude that the company has not demonstrated to staff that the current CODs [commercial operation dates] have a reasonable chance of being met.  It is our opinion that there exists a strong likelihood of further delayed operation dates for both units.”

Continue reading Time For A Reality Check: