Tag Archives: Georgia Power

New Analysis
 Begs The Question:
 Is Vogtle Project
 Too Costly To Complete?

Last week’s headlines focused on Georgia Power’s newly signed agreement with Toshiba committing (recommitting?) the Japanese parent of bankrupt Westinghouse to pony up $3.68 billion to fund the completion of the long-delayed Vogtle 3 & 4 nuclear power plants. While that is clearly good news (at least for the moment) for Georgia ratepayers, who could otherwise have been stuck with the bill, it has obscured the real news—that no one knows how much it is going to cost or how long it is going to take to complete the two reactors.

The day before Georgia Power’s headline stealing news, staff and the independent construction monitor filed testimony at the Georgia Public Service Commission covering the latest six months of activity at the site (from July 2016-December 2016, with rollover analysis through April 2017). Their conclusion? The project has been a mess since the beginning, and there are still no signs of improvement (although admittedly couched in far more diplomatic/technical language, to which we now turn).

At the macro level, much of the problem can be traced to the absence of a credible integrated project schedule or IPS, an absolute must in a project as complex as this, William Jacobs, Jr., and Steven Roetger told the commission. Jacobs has served as the project’s independent construction monitor since 2009; Roetger is the commission’s lead analyst for the project. They have been highly critical of the Southern/Westinghouse work at Vogtle for years and have warned consistently that the stated completion dates bore no relationship to reality; see my stories here and here.

Continue reading New Analysis
 Begs The Question:
 Is Vogtle Project
 Too Costly To Complete?

Looking At The Brackets:
 New Nuclear Plants
 Are Odds-On Favorite
 To Lose In First Round

I just finished filling out my March Madness brackets (for recreational purposes only, I assure you), so I think we also should start a pool on when the next utility will ask its state regulators for permission to build a new, large-scale nuclear power plant? If we did, should ‘never’ be one of the options?

Anyone willing to put their money on Georgia Power? The company actually had gotten state approval to do some preliminary work at a possible site for two new reactors In Stewart County on the border with Alabama. But earlier this month the utility told regulators it was suspending work on the expansion plans at least until its 2019 integrated resource plan is filed.

How about Florida Power & Light? The company’s planned two-unit expansion at Turkey Point has been on the books since 2008, when FPL was optimistically forecasting the new reactors would be up and running by 2018 and 2020, before subsequently pushing the start-up back first to 2022 and 2023 and now to 2027 and 2028. But last year the company told Florida regulators that while it still intended to secure its NRC license for the facility (which is expected sometime this year), it didn’t intend to do anything else until 2020.

Finally, how about Dominion Resources, which has been pushing for years to add a third unit to its North Anna site in Louisa County, Va. The proposed reactor, a 1,470 MW design developed by GE and Hitachi known as the ESBWR (Economic Simplified Boiling Water Reactor), is a first-of-its-kind unit with an estimated capital cost of almost $15 billion and an all-in cost of about $20 billion. Despite its enthusiasm for the project, even Dominion acknowledged in its 2016 IRP that the reactor was only economic in one scenario—full implementation of the former Obama administration’s soon-to-be defunct Clean Power Plan.

The problems for these companies, and any others considering such a step, go well beyond the well-documented, and still far-from-over cost overruns and delays that have plagued the four new reactors currently under construction in Georgia and South Carolina. The real issue is that the technology—one with high capital costs requiring a long time of steady state operation to get into the black—doesn’t mesh with the nation’s rapidly evolving electric power system. Committing to a nuclear plant constrains you for at least 40 years, and perhaps for as long as 80 years; and while you are still committed, everything else is changing.

Continue reading Looking At The Brackets:
 New Nuclear Plants
 Are Odds-On Favorite
 To Lose In First Round

Time For A Reality Check:
 More Delays Are Coming
 For Georgia Power’s
 New Vogtle Reactors

Georgia Power executives certainly won’t say it and Georgia’s utility regulators certainly won’t acknowledge it, but the reality is there are going to be additional delays at Vogtle 3&4—the already delayed and over budget new nuclear project being built by Westinghouse for the Southern Company subsidiary and a consortium of Georgia municipal utilities south of Augusta.

In a process that resembles a Kabuki dance, every six months Georgia Power is required to file a construction monitoring report with the Georgia Public Service Commission detailing its progress and justifying its expenditures in the last reporting period. (Georgia Power filed its 14th such report, covering the six months from June-December of 2015, in February 2016; it is now pending before the PSC.) Intervenors get to comment during this process, but once that is done, like clockwork, the commission signs off on the report, the utility gets to charge ratepayers for the approved expenses and the whole process starts anew. However, when you look closely it is clear that all is not well with the long-running Vogtle production.

In particular, it is worth taking a long look at the testimony presented by Dr. William Jacobs and Steven Roetger, who represent the Georgia PSC’s public interest advocacy staff in overseeing construction activities at Vogtle. Jacobs is the project’s independent construction monitor and has raised questions about the plant’s construction schedule virtually since the first dirt was turned (see this story). Roetger is the leader of the staff’s oversight team and has been involved with the project since the beginning. We will get into the details of their testimony below, but their conclusion is striking:

“We conclude that the company has not demonstrated to staff that the current CODs [commercial operation dates] have a reasonable chance of being met.  It is our opinion that there exists a strong likelihood of further delayed operation dates for both units.”

Continue reading Time For A Reality Check:
 More Delays Are Coming
 For Georgia Power’s
 New Vogtle Reactors

What Is Prudent?
 Red Flags Clearly Ignored
 In Vogtle 3&4 Project

Georgia Power is in the midst of a prudence review of its spending at the Vogtle 3 and 4 nuclear project—a review that undoubtedly will be lengthy, comprehensive, and mind-numbingly dull, turning on such issues as whether given decisions were “reasonable given the facts and circumstances which were known or reasonably should have been known at the time the decision was made.”1The real question though isn’t whether Georgia Power has spent customers’ money (and believe you me it is customers, not the utility, that are paying for this long-delayed, much over-budget project) prudently, but where the hell the adults where when the decision was made to go ahead with construction in the first place.

A close review of Georgia Power’s own documents (the filing can be found here) in the case shows two things: First, there were red flags aplenty when someone, anyone in the decisionmaking process would have been justified in standing up and saying, ‘Hey, wait a minute, what are we thinking?” Second, executives at Georgia Power apparently are color-blind and can’t see the color red, and continue to insist that everything—and I mean everything—they have done during the past decade to build the two new Vogtle units has been appropriate. For example, writing in the introduction to the company’s 885-page filing to the public service commission, Paul Bowers, Georgia Power’s chairman, president and CEO, offered up this classic: “Every dollar, and every day, that has been invested has been necessary to complete these new units safely and correctly. Our reports will establish that the new units could not have been built for less money or in less time than it has taken.” That may be, but that kind of logic can justify almost any expenditure. If the utility had paid attention to the red flags hanging everywhere it might have more accurately estimated the project’s cost and required construction time in the first place, which in turn might have led to a different decision by the commission.

The problems with the project go back to the very beginning. For starters, what were Georgia Power and Westinghouse executives thinking in April 2008 when they signed an engineering procurement and construction (EPC) contract for the two new nuclear units that was essentially a fixed price affair—even though detailed design drawings for the reactor’s construction were still years from completion, meaning, for the clear-eyed, that the contract price was little more than an estimate scribbled on the back of a cocktail napkin.

Continue reading What Is Prudent?
 Red Flags Clearly Ignored
 In Vogtle 3&4 Project