Tag Archives: Westinghouse bankruptcy

New Analysis
 Begs The Question:
 Is Vogtle Project
 Too Costly To Complete?

Last week’s headlines focused on Georgia Power’s newly signed agreement with Toshiba committing (recommitting?) the Japanese parent of bankrupt Westinghouse to pony up $3.68 billion to fund the completion of the long-delayed Vogtle 3 & 4 nuclear power plants. While that is clearly good news (at least for the moment) for Georgia ratepayers, who could otherwise have been stuck with the bill, it has obscured the real news—that no one knows how much it is going to cost or how long it is going to take to complete the two reactors.

The day before Georgia Power’s headline stealing news, staff and the independent construction monitor filed testimony at the Georgia Public Service Commission covering the latest six months of activity at the site (from July 2016-December 2016, with rollover analysis through April 2017). Their conclusion? The project has been a mess since the beginning, and there are still no signs of improvement (although admittedly couched in far more diplomatic/technical language, to which we now turn).

At the macro level, much of the problem can be traced to the absence of a credible integrated project schedule or IPS, an absolute must in a project as complex as this, William Jacobs, Jr., and Steven Roetger told the commission. Jacobs has served as the project’s independent construction monitor since 2009; Roetger is the commission’s lead analyst for the project. They have been highly critical of the Southern/Westinghouse work at Vogtle for years and have warned consistently that the stated completion dates bore no relationship to reality; see my stories here and here.

Continue reading New Analysis